Land Information Memoranda (LIM) Guide

Find a Property Valuer in NZ

A LIM? What is it?

A LIM is a Land Information Memoranda. It's a document that, by law, a Council has to provide for any property within its borough within 10 days of request.

Anyone can request a LIM about any property; you do not have to be the owner, or potential purchaser.

The council that covers the area that the property is in will have a file containing information relating to that house; it's a summary of the content in this file that is contained in the LIM.

A LIM can include a lot, or a very small amount, of information depending on the history of the property, where it is, and when and how often there has been council involvement with the property.

Officially a LIM is a document produced by a territorial authority (Council) that contains a summary of any relevant current and historical information held by the council about a particular piece of land or property.

Back to top

Why should I get a LIM?

Back to top

What is in a LIM?

A LIM is a comprehensive report containing everything the Council knows about a property or section and can include:

  • Valuation data
  • Yearly rates payable for the property.
  • If there are any unpaid rates.
  • Any charges for water.
  • Information about Building Permits and Consents for the property.
  • Any information in regards to whether it is a protected or historic building, or site, and if there are any protected trees.
  • Any Resource Consents issued for the property.
  • Any relevant planning issues or planning zones that impact the property.
  • Any Resource Consents issued in the immediate neighbourhood.
  • Information on subdivisions and developments affecting the property and the immediate area.
  • Drainage information relating to both private and public sewer and / or storm water on the property.
  • Special land features including potential erosion, avulsion, falling debris, slippage and possible hazardous substances.
  • Consents, certificates, notices, orders or requisitions affecting the land or buildings.
  • District Plan classifications that relate to the land or buildings.

The LIM will be up-to-date and contain a summary of all the information a council has on its files as of the day it is issued.

Back to top

I've got my LIM - now what do I do?

It is a good idea to look over the LIM with your lawyer when you receive it. Your lawyer's experience and expertise regarding LIMs, combined with your knowledge of the property and your thoughts on what you intend to do with the property, will ensure that the LIM is understood and the full implications of any aspects of the LIM are realised.

Read through the summary pages - potential issues are likely

to be obvious here. Then dive into the main contents of the LIM. Look for outstanding financial obligations, resource consents, building permits, and related plans. Check that all issued consents have been signed off. For building work from 1992 onwards, check that a code of compliance certificate has been issued for works completed.

Take your personal knowledge of the property, its buildings, retaining walls, land use and the surrounding properties and the area and consider that against the information contained in the LIM. You should ask questions of the seller and the council if you find differences.

Get expert help if you need it!

Consider what impact the findings of the LIM will have on your enjoyment of the property and the value of the property.

Back to top

Even a LIM has limits

The council won't report on information that is not relevant nor reliable. There may be a lot of information about a property, but the report will only include what is legally required to be in a LIM. Finally, there could be information regarding the property that the council just doesn't know, so keep this all in mind!

Councils are not legally obliged to hold information relating to building work prior to the Building Act 1991. In older properties it is possible that Council records prior to 1991 are incomplete, and consequently Councils do not accept responsibility for the accuracy or completeness of those records.

Some elements of the property may be excluded from LIMs. For example, installations of septic tanks, gas bottles, etc. If these types of installations are on the property you may need to seek expert advice on these items.

Additionally, the council will not carry out a visual inspection of the land or buildings to verify the accuracy of information or determine the current condition of the property. For example, the survey measurements of boundaries may not be accurate on council records. Also, Councils will not show illegal or unauthorised work on the property if it is not known to them.

Back to top

How much does a LIM cost?

The cost of a LIM varies from council to council, but they generally range from $150-$400. To find out the cost of a LIM, check you local council's website or give them a ring.

Back to top

A LIM as a condition of sale

If you want a LIM as a condition of sale, you need to state this in your sale and purchase agreement. As a LIM takes up to 10 working days to process, to save stress, you should allow yourself 15 days for satisfying your conditions. This will give you time to apply for the LIM, and time for both you and your lawyer to read the LIM over before deciding about going unconditional.